October 2025
Topping off
Summer 2025
Framing continues
March 2025
Mass timber mobilization and framing begins
November 2024
Steel reinforcement of fly tower begins
October 2024
Foundation is completed
June 2024
Ground is broken
March 2024
Site preparations begin, construction scrim erected
October 2023
Project approved by the Boston Planning & Development Agency